Quality Assurance in Civil Engineering: Flow-Diagram Practice
Purpose of Task
This task provides learners with a visual learning approach, demonstrating how QC/QA processes are sequenced and integrated in civil engineering projects. Learners will complete a flow diagram showing inspection, reporting, escalation, and corrective action, ensuring compliance with UK regulations and standards.
Scenario:
You are the QA/QC Officer on a multi-storey commercial building project in London. During routine inspection, a beam reinforcement placement deviated from the approved design specifications. As per project procedures, the non-conformance must be addressed, documented, and escalated according to UK regulations and company QA/QC standards.
Relevant standards and legislation:
- BS EN ISO 9001:2015 – Quality management system, process control, and continual improvement
- Construction (Design and Management) Regulations 2015 (CDM 2015) – Roles and responsibilities, risk management
- Building Regulations 2010 (as amended) – Structural integrity and workmanship
- Health and Safety at Work Act 1974 (HSWA) – Integration of safety in quality processes
Step 1: Define Key Processes to be Sequenced
The flow-diagram should include the following key QA/QC processes:
- Initial Inspection – Identify non-conformance during routine QC checks.
- Document Non-Conformance – Complete Non-Conformance Report (NCR) including location, description, and specifications violated.
- Immediate Corrective Action (if required) – Stop work or isolate defective element to prevent further issues.
- Notify Stakeholders – Inform site supervisor, project engineer, and QA Manager.
- Analysis and Root Cause Investigation – Determine why the non-conformance occurred (human error, material issue, design misinterpretation).
- Corrective Action Planning – Propose measures to rectify the nonconformance (rework, replacement, process modification).
- Approval of Corrective Action – QA Manager or Project Engineer approves plan in compliance with BS EN ISO 9001:2015.
- Implementation of Corrective Action – Execute rectification under supervision.
- Verification and Re-Inspection – QA/QC team checks corrected work meets specifications.
- Close NCR and Record Lessons Learned – Document outcome for audit trail and continuous improvement.
Assessor Notes:
- Each process step must clearly show who is responsible and which UK legislation or standard applies.
- The flow-diagram demonstrates LO1–LO4, linking QC/QA principles to stakeholder responsibilities and compliance.
Step 2: Flow-Diagram Template
Learners are provided with a partially completed flow-diagram and are required to fill in missing steps, add responsible stakeholders, and map relevant legislation.
Example of Partial Flow-Diagram Table for Completion:
| Step | Description | Responsible Stakeholder | Relevant UK Standard / Legislation | Action Required |
| 1 | Initial Inspection | QC Inspector / Site Engineer | BS EN ISO 9001:2015, HSWA 1974 | Identify nonconformance, document findings |
| 2 | Document NCR | QC Inspector | ISO 9001:2015 | Complete NCR with details and photos |
| 3 | Stop Work / Isolate Defect | Site Supervisor | CDM 2015, HSWA 1974 | Prevent further use of defective element |
| 4 | Notify Stakeholders | QA Officer | ISO 9001:2015, CDM 2015 | Inform project manager, QA Manager, and contractor |
| 5 | Root Cause Analysis | QA Officer /Engineer | ISO 9001:2015 | Investigate deviation causes |
| 6 | Corrective Action Planning | QA Officer / Project Engineer | ISO 9001:2015, Building Regulations 2010 | Propose corrective measures |
| 7 | Approve Corrective Action | QA Manager / Project Engineer | ISO 9001:2015 | Review and approve plan |
| 8 | Implement Corrective Action | Site Team / QC Inspector | CDM 2015, Building Regulations 2010 | Execute plan and supervise work |
| 9 | Verification / Re-Inspection | QC Inspector / QA Officer | BS EN ISO 9001:2015 | Confirm nonconformance rectified |
| 10 | Close NCR / Lessons Learned | QA Officer / Project Manager | ISO 9001:2015 | Document outcome and update QA records |
Learner Task Instructions:
1. Complete the Flow-Diagram:
- Fill in any missing process steps, responsible stakeholders, and actions required.
- Ensure each step references UK legislation or standards.
2. Create a Visual Flow-Diagram:
- Convert the table into a visual flow chart showing sequence of processes, decision points, and escalation paths.
- Include arrows for flow, decision diamonds for approvals, and boxes for each process step.
3. Reflective Analysis:
- Explain why each step is necessary in ensuring quality and regulatory compliance.
- Discuss differences between QC (reactive inspection) and QA (preventive planning) in the flow.
- Identify stakeholders responsible for compliance and corrective actions.
4. Scenario Application:
- Apply your flow-diagram to a hypothetical civil engineering scenario, e.g., foundation pour, beam reinforcement, or cladding installation.
- Show how NCRs, escalation, and corrective action maintain compliance with UK regulations.
5. Submission Requirements:
- Length: 3–4 pages (including visual diagram)
- Include headings, tables, and flow-diagram visuals
- Reference all UK laws and standards (ISO 9001:2015, CDM 2015, Building Regulations 2010, HSWA 1974)
Expected Learner Outcomes
Upon completing this task, learners will be able to:
- Visually sequence QA/QC processes from inspection to corrective action.
- Understand the roles and responsibilities of stakeholders at each step.
- Link each process step to UK legislation and standards.
- Distinguish between reactive quality control and proactive quality assurance in practice.
- Demonstrate practical skills in flow-diagram creation and process documentation for civil engineering projects.